Brand logo
HomeAutomationSupply ChainSmart ManufacturingLogisticsEnergyGeneral
  1. Home
  2. /
  3. general
  4. /
  5. price-interconnection-slots-like-options

Affiliate Disclosure: This article contains affiliate links. We may earn a commission if you purchase through these links.

WorldIndustrialWeekly General | Queue Discipline Compared: Pricing an Interconnection Slot From PJM to the UK

By Oscar Murphy, Manufacturing Transformation Consultant · Field Practitioner, Industrial Weekly

Start with the number that reframed this debate: since 2023 PJM has taken a queue that sat above 140 gigawatts (GW) down to about 46 GW — not by studying projects faster, but by charging more to keep a place in line. The direct answer to what a connection right is worth follows: price it like an option with an expiry, or it becomes a free bet on someone else's timeline. This comparison reads the permitting bill and four queue regimes through that one lens: who pays when a right sits idle.

Why does a queue slot behave like a free option?

Conclusion first: a slot carries option value with none of the option's cost, so rational developers hoard them and the system absorbs the waste.

Filing an interconnection request has historically been cheap, so developers filed early and repeatedly — often in several places for the same project — to keep choices open, as the Institute for American Manufacturing's queue primer explains. Under the old serial study rules, a single speculative withdrawal forced every project behind it through restudy. Waits stretched, and defensive multi-filing started to look rational even to serious developers. That is a sequencing failure, not a character flaw.

The bill was high. Before 2023, PJM's serial process stacked up a backlog above 140 GW, with some resources waiting more than five years, per Introl's analysis of the PJM capacity shortfall. A new generator in PJM needs about eight years to reach operation while the capacity auction pricing its revenue looks ahead only two to three years — a mismatch that punishes anyone who joined the queue in good faith.

The cleanup worked because holding got more expensive. FERC's (Federal Energy Regulatory Commission's) 2023 reforms brought higher withdrawal penalties and milestone-based study requirements, and many RTOs (Regional Transmission Organizations) and ISOs (Independent System Operators) raised deposits, as Sina Finance's review of queue distortion recounts. Lawrence Berkeley National Laboratory's (LBNL's) 2025 queue report says the same from the demand side: the American queue is heavy with speculative and eventually infeasible projects, and developers routinely hold overlapping applications for one project, dropping hundreds of megawatts (MW) of phantom capacity in a single stroke once a site is chosen.

The newest LBNL numbers sharpen that picture. Its Queued Up 2025 edition counted roughly 8,200 projects actively seeking US interconnection at the end of 2025, representing 2,061 GW of generation and storage — down 10 percent from 2024 — and found that only 13 percent of the capacity that entered queues between 2000 and 2020 had reached operation by the end of 2025 (LBNL, Queued Up). A queue is a ledger of intent, not a pipeline of electrons.

That distinction keeps getting lost. Loud figures claiming data centers account for more than 90 percent of new power requests come from queue filings, and queue filings overstate real demand for exactly the reasons above. A queue counts applications filed; most applications die without ever drawing a watt. This is the same measurement trap our comparison of electrification share targets against interconnection queues flags: counting megawatts filed is not counting megawatts built.

Where does the Senate bill speed things up — and leave the back door open?

Conclusion first: the bill is strong on the front end and silent on the back end, so faster clocks lower the cost of carrying a dormant right.

The bill is the Bipartisan American Affordability and Jobs Act (BAAJA), a 417-page Senate draft released in late September, according to JD Supra. Congress was still debating it on Thursday, November 12, with a floor vote expected within days, as contemporaneous coverage of the greens' split records. Its scope runs wide: a federal buildout of long-distance transmission, a reworked National Environmental Policy Act (NEPA), reduced state authority under the Clean Water Act (CWA), and expanded state authority under the Endangered Species Act (ESA), per an earlier policy writeup. The coalition around it is odd. Evergreen Action, a climate group founded by alumni of Jay Inslee's 2020 campaign, backs the bill outright. The Wilderness Society and Earthjustice oppose it, Sierra Club wants major revisions, Al Gore is against it, and the AFL-CIO, the International Brotherhood of Electrical Workers, and the National Urban League support it. Missing from nearly every position paper is a duller question: what happens when a holder takes the approval and declines to build.

The draft does print hard clocks. It requires any party holding grid data needed for an interconnection, facilities, feasibility, or affected-system study to produce it within 15 days, per JD Supra's bill analysis. The 150-day review clock matches the House-passed SPEED Act, and the Department of Energy (DOE) would study transmission congestion every three years, per the Bipartisan Policy Center explainer. Each deserves support. My quarrel is with what they leave unpriced: every week shaved off a study cycle makes a dormant position cheaper to carry and brings a speculative filer to a durable approval sooner, and nothing in the public bill summaries gives that approval an expiry date tied to construction.

The demand side shows what unpriced optionality attracts. ERCOT (Electric Reliability Council of Texas) is carrying more than 474 GW of interconnection requests, about nine in ten tied to data centers, spread across more than 1,800 projects — a stack more than five times the historical peak load, according to a briefing on the Texas standoff published on Eastmoney's Fortune channel. Texas has already paused new data center interconnection approvals by executive order in August 2026 and froze related environmental permits on September 21, and exit polling on November 3 found 75 percent of surveyed voters against new data centers in their own communities. Compute gear lands on quarterly cycles while grid increments arrive on decade scales, the timing gap a NetEase analysis of AI infrastructure timing describes. Filing everywhere is the hedge against that gap, and 474 GW is what the hedge looks like in aggregate.

Which commitment tools work? PJM, ERCOT, France and the UK compared

Conclusion first: every regime that has cut phantom capacity uses the same three levers — a deadline, a deposit, and reallocation — but they differ on when the screen bites and what they dare not demand upfront.

Design work exists on both sides of the Atlantic, so the bill would be assembling known parts. France's reform introduces a milestone logic under which a sponsor must clear documented steps at specified dates or surrender the queue position, and it deliberately stops short of demanding all permits and full financing upfront; the backdrop is 33 GW of industrial capacity stuck behind outdated rules, per a report from the French site Journal du Progressiste. Stateside, ERCOT's zero-batch track makes developers prove project maturity before entering a regional transmission study, SPP (Southwest Power Pool) runs its HILLGA framework for large loads, PJM operates a dedicated large-load procedure, and NRG Energy has proposed competitive open-recruitment windows with time-limited bidding that would charge large users for the grid upgrades they trigger, per Sina's coverage of the commitment-first shift.

A fourth case is now in view. Ofgem approved NESO's connections-reform methodology, TMO4+, in April 2025, replacing "first come, first served" with "first ready, first connected" and establishing Gate 1 and Gate 2; customers clearing the reform are expected to receive Gate 2 offers with confirmed dates, with connections phased into 2026–2030 and 2031–2035 (NESO connections-reform timeline; Ofgem). It is the same direction of travel — screen for readiness before spending study capacity — but a different mechanism: a readiness gate rather than a deposit.

RegimeCore leverWhen the screen bitesCost to a holderWhat it has not yet proved
PJM (2023 reforms)Withdrawal penalties, milestone studies, new minimums effective January 1, 2027 (at least 85 percent of contract demand at transmission and distribution level, 60 percent at generation level)At each study milestonePenalties and depositsWhether the reformed queue, due to finish processing by end of 2026, clears real projects
ERCOTZero-batch track requiring proof of maturityBefore regional transmission studyDenied entry if immatureLong-run delivery; track is young
SPPHILLGA framework for large loadsLarge-load entryMaturity screeningPublic completion data
FranceMilestone logic; surrender position if steps missedSpecified datesLoss of queue position, not full permits or financing upfrontDelivery against a 33 GW blocked-capacity backlog
GB (Ofgem/NESO, April 2025)TMO4+ "first ready, first connected," Gate 1/Gate 2Readiness gatesDeprioritisation if not readyConnection windows 2026–2030 and 2031–2035 not yet delivered

The trade-off is visible in the table. Deposit-and-penalty systems (PJM) price the option directly but can favour deep balance sheets. Readiness-gate systems (ERCOT, GB) filter earlier without charging cash but can be gamed by paperwork. Milestone systems (France) occupy the middle. None of this is theoretical: the bill's own 15-day clause shows its drafters understand a hard clock with a number printed on it.

What would it cost to put a price on the slot?

Conclusion first: three clauses fit the existing architecture, and the money at stake is already showing up on customer bills.

Extending the bill's clock discipline from documents to capacity needs no new theory. A withdrawal deadline keyed to study milestones, so an inactive application exits before it forces another restudy cycle. A staged deposit — modest at filing and stepped up at each milestone — refunded or credited against interconnection costs on completion, which puts a carrying cost on the option without prohibiting it. Automatic reallocation for corridor approvals, so a transmission right that misses construction milestones returns to the planning pool instead of aging in a drawer. Corridor language deserves equal billing with queue language, because the federal transmission buildout this bill envisions will mint precisely these long-lived approvals.

Who pays for idle capacity is no longer hypothetical. Researchers for the Virginia legislature found a typical residential customer could carry an extra 14 to 37 dollars per month in generation and transmission costs by 2040 in real terms absent rate restructuring, per the Introl analysis. Virginia regulators cut Dominion's requested increases for 2026 and 2027, 822 million and 345 million dollars, down to approved amounts of 565.7 million and 209.9 million dollars. The facts sit on the public record; the reading is mine. Voters punish cost shifting, regulators are migrating to commitment-based rules, and a bill that accelerates approvals while letting granted rights idle for free is swimming against its own politics.

Who gets filtered out — and what would prove this wrong?

Conclusion first: the fairness objection is real but answerable, and the whole case should be treated as a test with a kill criterion.

Common misconceptions, and the data answer

  • "A priced queue just selects the deepest pockets." Deposits and maturity screens do filter by balance sheet. A hyperscaler or a utility affiliate can post staged deposits across many sites without noticing; a small storage developer cannot, and that developer may genuinely need the queue data, the study results, and the preliminary engineering to raise the financing that would make it mature. Compel commitment before the information that produces commitment exists, and the queue cleans up by washing out small players. The answer is a refundable, milestone-staged deposit sized to project capacity — it keeps the multi-site strategy legal while giving it a carrying cost a small shop can afford.
  • "Delays come from admission rules." The Data Center Coalition's filings hold that delays stem mainly from undersized transmission planning and missing long-range planning, with admission rules a minor factor, so penalties would treat a symptom. The bill's triennial congestion study widens the lens, and wider planning reduces the incentive to file defensively everywhere; fewer defensive filings in turn make stricter queue discipline cheaper to bear.
  • "The model is proven." It is not. France's milestone system and ERCOT's zero-batch track are young, and the evidence base is thin. I concede the point and convert it into a test.

The one clean data point we have cuts in favour of discipline: PJM's queue shed its duplicates after 2023 while the reformed process kept clearing projects, which suggests penalties remove filings that were never going to be financed anyway. The test is explicit. If completed capacity in jurisdictions running commitment-first rules falls over the next two years relative to jurisdictions without them, the case for dormancy penalties collapses and this argument is wrong. If withdrawals keep shedding duplicate megawatts while completions hold, the case stands. That is why our construction-side reading of the same bill argues for publishing construction start, queue closure and dispute data as the only honest scorecard.

Even the supporters concede the implementation layer decides outcomes. On the Shift Key podcast, hosted by Heatmap News founding editor Robinson Meyer, executive director Lena Moffitt and vice president of policy Pete Wyckoff argued that major changes at FERC remain necessary even if the legislation clears, per the recap of the greens' split. Moffitt's pre-vote statement held that no better deal is around the corner and that the country has to start building clean energy at scale. A group endorsing speed while acknowledging regulators must finish the job should have no trouble accepting dormancy clauses, since the clauses are that finishing work.

Decision guide: a replicable framework for queue discipline

Conclusion first: your stance follows your position in the queue, not your ideology — and the same three-lever framework applies wherever a scarce connection right is handed out free.

  • Mature, single-site holders gain relative standing each time a deposit or deadline lands; they should support discipline and publish their completion data.
  • Speculative multi-filers lose a free option; expect lapses and price the hedge accordingly.
  • Utilities carrying dormant corridor rights should expect lapse clauses in whichever bill or FERC docket moves next.
  • Small developers should push for refundable, capacity-scaled deposits plus public study data, so the screen tests maturity rather than cash on hand.

The framework is deliberately portable — background, mechanism, key metrics, replication conditions. Step one, identify the scarce right (a queue position or a corridor approval). Step two, attach a clock with a number printed on it. Step three, add a staged, refundable deposit that prices the carry without banning the hedge. Step four, write automatic reallocation so a missed milestone returns the right to the pool. Step five, pre-commit to the kill criterion above. That is the whole retrofit; it needs no new statute beyond the one already on the floor.

The calendar that decides it is concrete: the Senate vote following the November 12 debate, ERCOT's queue review report due December 10, 2026, and the Texas legislative session running January 12 through May 31, 2027, where the pauses could harden into law. PJM's reformed queue is supposed to finish processing by the end of 2026, so its withdrawal and completion statistics will be the first clean test of whether discipline kills real projects. Dustin Meyer, who has testified before the U.S. Senate on the need for reform, put the consensus plainly on LinkedIn: "We work a lot of wonky/technical issues, but permitting reform isn't one of them." The dispute is over the fix, and the fix has to cover the back of the process as well as the front. Charge rent on the slots before the clocks speed up, or Congress will have built the fastest approval machine speculative capital has ever used.

FAQ

Is an interconnection slot really an "option"?

Yes, in the financial sense — a right, not an obligation, to connect. Because filing was cheap and withdrawal painless, that right carried no premium. PJM's fall from above 140 GW to roughly 46 GW shows what happens when a carrying cost is introduced.

Would deposits shut out smaller developers?

They can, if the deposit is flat and non-refundable. A staged deposit that is refunded or credited on completion, and scaled to project capacity, prices the hedge without banning it. The small-developer objection is about the timing of information, not about whether discipline is desirable.

Doesn't the Senate bill already fix the queue?

It fixes the front end: 15-day data production, a 150-day review clock, and a triennial congestion study. It does not attach an expiry to a granted approval, so a faster front door also makes idle rights cheaper to keep.

What is a "corridor approval," and why does it matter here?

It is the right to build transmission along a route. The bill's federal transmission buildout would create many such long-lived rights; without automatic reallocation, a route that misses construction milestones can sit unused in a drawer.

What evidence would change the conclusion?

Completed capacity in commitment-first jurisdictions falling, over the next two years, relative to jurisdictions without those rules. If that happens, the case for dormancy penalties collapses.

References

  • BAAJA Blast: What the Senate Permitting Bill Means for Transmission Developers (JD Supra)
  • Senate Unveils Bipartisan Permitting Overhaul (JD Supra)
  • Explaining the Senate Permitting Bill (Bipartisan Policy Center)
  • PJM's 6 GW Capacity Shortfall (Introl)
  • The Interconnection Queue (Institute for American Manufacturing)
  • Queued Up: Characteristics of Power Plants Seeking Transmission Interconnection (LBNL)
  • In France 33 GW of Capacity Stuck by Outdated Rules (Journal du Progressiste)
  • Speculative queue filings distort perceptions of grid demand (Sina Finance)
  • Texas 2026: interconnection and permitting pauses (Eastmoney Fortune)
  • From interconnection queues to compute deployment (NetEase)
  • Duplicate filings push grid planning toward commitment first (Sina News)
  • Connections reform timeline (NESO)
  • Moving to a reformed grid (Ofgem)
  • Coverage of Evergreen Action and the greens' split
  • Earlier writeup on Evergreen Action and the Senate bill
  • Fixing Broken Permitting System for Energy Infrastructure (LinkedIn, Dustin Meyer)

Related reading

  • Judging the Senate Permitting Bill on Delivered Megawatt-Hours | WorldIndustrialWeekly General
Brand logo

Industrial Weekly

In-Depth Weekly Insights on Manufacturing & Supply Chain

AutomationSupply ChainSmart ManufacturingLogisticsEnergyGeneralGreen CarbonWorld

© 2026 Industrial Weekly.

Cookie Notice

We use cookies to improve your experience and analyze website traffic. Read our Privacy Policy to learn more.