No. A review clock shortens only the paperwork slice of a grid schedule. The Senate's Bipartisan American Affordability and Jobs Act (BAAJA) puts deadlines on studies, data delivery and appeals, while the constraints that actually stop a project — land control, financing, cost allocation, local consent and physical mobilisation — sit outside those clocks. Reform becomes visible delivery only if agencies publish construction-start, queue-closure and dispute records next to the deadlines they set.
Read the numbers as a schedule, not as a policy debate. In PJM, an AI infrastructure project reportedly takes more than seven years from planning to energization, while the building itself may take 12 to 18 months; interconnection studies reportedly run about 40 months against a target of 8 to 11 months. That gap is not a rhetoric problem. It is where capital sleeps.
Conclusion first: the administrative clocks are real and worth keeping, and they cover documents, not steel. GreencarbonWorld reported that BAAJA cleared a major Senate test after 73 senators voted to end debate, and described the next stage as a healthy amendment process. The Saturday morning manager's amendment, also reported by GreencarbonWorld, keeps regional transmission planning, cost allocation and a federal siting backstop while responding to environmental, tribal, utility and data center objections, and the Senate text discusses 230-kilovolt lines and related transmission mechanics.
On the timing side, Climate Solutions Law said the proposal reportedly includes a 150-day window to challenge approvals plus a review standard affecting remand outcomes. JD Supra noted that a party holding interconnection study data needed for a facilities, feasibility or affected-system study would have to provide it within 15 days. A federal order requires six regional operators to address large load pricing within 60 days and deliver reliability reports within 30 days. Those are enforceable, checkable and useful. None of them say anything about the day a transformer lands on a foundation. For the delivery and price side of the same package, our BAAJA scorecard of transmission upside and review clocks is the companion read.
Because the failure rate is upstream of approval and downstream of it. An East Money report said the average project in an interconnection queue had waited 4.8 years, citing Interconnection.fyi and academic sources. A senior infrastructure analyst at the Center for American Progress argued that most queue projects eventually fail to be built, with 72 percent of applications from 1999 to 2018 withdrawn. The same report cited FTI research saying fewer than 20 percent of applications filed between 2000 and 2018 were operational by the end of 2023.
Lawrence Berkeley National Lab compiled queue data through the end of 2025 in its Queued Up analysis, and an OSTI record describes the same interconnection queue work. An East Money Creative report said that as of the end of 2025 there were about 8,200 projects in U.S. interconnection queues, involving 1,312 gigawatts of generation capacity and about 749 gigawatts of storage, with a median wait of more than five years for projects reaching commercial operation in 2025, more than 70 percent of capacity submitted between 2000 and 2020 withdrawn by the end of 2025, and less than 20 percent built. A regular public inventory is already the baseline: if regulators accept a national queue report, they can accept a national project report.
Two things the master narrative skips are worth adding here. First, queue screening already exists. FERC Order No. 2023, adopted in 2023, requires transmission providers to impose escalating withdrawal penalties when a withdrawal materially affects other customers' study costs, precisely to deter non-viable projects from entering or staying in the queue. Screening is therefore a solved problem in policy terms; post-approval physical tracking is not. Enverus, which tracks queue decisions for developers, notes that historical interconnection queue withdrawal rates hover around 80 percent — a number that should make any operator treat queue capacity as intent, not supply.
Second, the physical scoreboard already tells the story. The Alliance for Clean Energy New States and Grid Strategies reported in July 2025 that only 322 miles of new high-voltage transmission line were completed in 2024, against nearly 4,000 miles built in 2013 alone; Utility Dive summarized the same series as averaging 925 miles a year from 2015 to 2019 and 350 miles a year from 2020 to 2023. Approvals can rise while energized miles keep falling, and an approval-only dashboard would hide exactly that. Note also that different public tallies of "miles built" disagree depending on voltage threshold and whether upgrades count as new line — an argument for publishing one definition rather than three.
Another gap sits between announcement and local reality. A Wall Street CN report said Barclays participants estimated permitting efficiency had fallen about fourfold, and that many announced data center projects had not received local approval or completed interconnection applications. It cited Ballotpedia data showing 41 ballot questions covering bans, pauses, review requirements, zoning changes and project-specific rezonings: seven advisory measures favoring construction were defeated, while 17 direct construction bans passed. More than 85 percent of data center projects were reportedly seeking construction insurance extensions because of delays. A developer can clear a study and still stall at land, financing, cost allocation, power purchase terms or community litigation. NetEase reported that investor-owned utilities through the Edison Electric Institute wrote to legislators in support, and that utility operators are the main executors of transmission investment — the delivery consequences of that point are laid out in our case study of how the grid section would change transmission delivery.
A construction start should mean more than a groundbreaking photo. It should require verifiable markers such as site clearing, major equipment orders, civil works contracts or recognized capital expenditure, with thresholds that vary by project type: a 230-kilovolt line and a solar farm do not share physical milestones, but both can be tracked by whether money and equipment have moved into the ground. Energy Solutions projected that its modeled new queue system could reduce median connection offer delay from seven years to an 18-month target, raise commitment fees from below 0.01 percent of capital expenditure to 2 to 5 percent, and cut speculative queue entries by 60 to 80 percent.
| Field | What it proves | Where it comes from |
|---|---|---|
| Approval date and pathway | Whether a project cleared a full study or an expedited route | Agency permit logs |
| Queue status and withdrawal reason | Whether capacity is intent or supply | Regional operator filings |
| Cost allocation decision | Who pays, and whether finance can close | Regulatory dockets |
| Land or right of way status | Physical access, not paper access | Utility filings, recorded deeds |
| Capital milestone | Equipment ordered, civil works contracted | Purchase notices, capex reports |
| Energization date | The only field the grid notices | Operator commissioning records |
| Dispute open and close dates | How long legal risk actually binds a site | Court docket entries |
| Consent tag | Whether zoning or ballot challenges stopped mobilization | Local clerk records, Ballotpedia-class data |
Reporting should be phased so it survives its first budget cycle. Year one relies on existing data from regional operators and the Federal Energy Regulatory Commission. Year two publishes definitions. Year three attaches consequences, and those consequences should land on the authority using the reform — eligibility for expedited treatment, federal cost allocation, future planning preference — not as personal fines for developers or judges. The reporting body should be separate from the agency that wants to appear faster.
The honest objection is that construction metrics are harder to police than review metrics. Five failure modes are worth naming, because most permitting coverage ignores them.
Only the document part. Interconnection data delivery, review schedules and challenge windows get clocks; energization still depends on land, equipment slots, financing and local approval.
No. Deadlines are the right tool where delay is administrative — document completeness, data delivery, environmental schedules, challenge windows. Physical metrics are the right tool where delay is capital or land.
Site clearing, major equipment orders, civil works contracts or recognized capital expenditure, each verifiable in public filings, with thresholds set by asset class.
A body separate from the agency seeking credit for speed, drawing on utility filings, permit logs, purchase notices, court dockets and queue status, released on a fixed cadence.
Copyable frame, three lines per project and one quarter of history each: Clock — approval date, pathway, days elapsed against deadline. Capital — land or right of way held, equipment ordered, civil works contracted, energization scheduled. Consent — comments addressed, challenge filed, challenge closed. A project that looks healthy on all three lines will be built; a project green only on Clock is a press release, and BAAJA should be judged on how fast it makes that distinction public.