Projects that came online in the United States in 2025 had spent an average of eight years in the interconnection queue before they could energize, according to a Novogradac review of that year's completions. That gap is the practical test of COP31's 35x35 pledge: a share can be met on paper while the capacity behind it waits for a wire. The fix is not a new global target but a comparable connection metric — a voluntary annex covering queue length, withdrawal rates and upgrade-cost allocation.
The 31st conference opened in Antalya with electrification as its main agenda item. Turkey's presidency wants electricity to supply 35% of the world's final energy use by 2035, a figure that will be quoted in ministerial communiqués for a decade. What the text does not carry is any measure of whether the projects meant to supply that electricity can reach the grid.
It measures a share, and the share rests on a contested denominator. Reporting on the opening session put electricity at 21% of end-use energy and cited a Rhodium Group projection of 28% by 2035. The World Benchmarking Alliance describes the presidency's proposal as a rise from roughly 23% of final energy consumption to 35% by 2035, and Down To Earth uses the same 23% starting point. Two points of difference is easy to wave through and big enough to settle who gets to claim success.
That gap is not carelessness. End-use energy and final energy consumption place the system boundary differently, and efficiency, fuel switching and international bunkers land on different sides of the line. Shift the convention and a country can report 35% on the back of a redefinition plus ten years of efficiency gains while adding almost no connected capacity. Settling the denominator comes before counting signatures.
Even with the boundary fixed, the climb is steep. Rhodium's central path reaches 28% by 2035 while the pledge asks for 35%, which leaves seven points to close over ten years. Final demand has to grow slowly, clean generation has to scale, and networks have to connect new load and new supply at a pace most power systems have rarely managed. The first two show up in energy statistics. The third shows up in no headline indicator at all.
And a share can climb with no new wire at all: trim final energy demand through efficiency while electricity use holds, and the percentage rises while the grid does no extra work. Both effects are desirable; only one tests whether the pledge changed anything physical.
Because queues are now the binding constraint. The IEA's Electricity 2026 assessment reports grid connection queues at record levels worldwide and calls for annual grid investment to rise sharply through 2030 to keep pace with demand. Practitioners have tried to size the backlog: Alicia Argüello, writing on LinkedIn, estimates that more than 2,500 GW of renewable generation, storage and large-load projects are waiting for connection worldwide. That is one analyst's working number rather than an official census, and it should be read as an order of magnitude.
It is also a stock, while a 2035 target runs on a flow. A large waiting list says nothing about how long each project waits, how many applications are pulled, or how much of the total is speculative. A scheme can sit for six years, energize, and still be counted in 2035 — but it shows up late and no planner can rely on the date. Capacity connected before the pledge existed can satisfy the share without measuring anything the pledge did.
Lead times compound the timing problem. Transmission reinforcement and substation upgrades run to several years in many markets, so a queue that looks manageable today can eat the whole decade if it is not cleared early. Practice varies widely: a small distribution-connected solar array can be energized in months in one jurisdiction, while a transmission-level request elsewhere waits through study cycles, reinforcement work and re-bidding.
In developing countries the constraint bites earlier. ESI Africa frames the pledge for Africa around connections, cooking and who pays, and analysis at ecoltdgroup puts grid finance ahead of the share itself. Where the network was never built to reach a region, the queue is less a list of stalled projects than a list of projects nobody proposed. A diagnosis of China's distribution-grid reforms points at rules rather than wires: available capacity is now disclosed, but the mechanisms that separate speculative queue positions from viable projects, the triggers that release held capacity, and the principles for sharing upgrade costs still rest on administrative coordination instead of published rules.
Each field answers a different question, and none substitutes for another. Queue length is a stock; withdrawal rates are a rate of attrition; cost allocation is a survival test. A template needs all three because each one on its own can be gamed.
| Metric | What it measures | What it misses | Best used for |
|---|---|---|---|
| Queue length (projects, MW) | Capacity waiting for a connection | Processing speed, attrition, speculation | Cross-market and year-on-year stock comparison |
| Withdrawal rate | Share of applications abandoned | Why they were abandoned | Separating speculative from serious projects |
| Upgrade-cost allocation | Who pays for reinforcement | Whether the project survives the bill | Project bankability and siting decisions |
Queue length gives a stock that compares across markets and years. Withdrawal rates do different work: they separate speculative applications from serious ones, and they cut both ways — a big queue that sheds most of its applicants can be moving faster than its headline size implies, while a quiet queue may simply be closed to newcomers. Cost allocation decides whether a project survives after it clears the gate, because the reinforcement invoice is where a lot of projects die.
The United States offers the most complete public dataset, and it shows both scale and churn. Lawrence Berkeley National Laboratory's Queued Up series counted about 8,200 active projects at the end of 2025, representing 1,312 GW of generation and roughly 749 GW of storage; a year earlier the count was about 10,300 projects and roughly 2,290 GW of generation and storage combined. The 2023 peak reached 2,600 GW against an installed U.S. fleet of about 1,280 GW, according to the University of Chicago's Sustainability Dialogue. Completion rates explain the gap: historically only about 20% of proposed capacity in PJM's queue was ever built, and the projects that do finish are slower — the average time from request to commercial operation rose from under two years in 2008 to nearly five years by 2024. RMI's analysis of PJM attributes the attrition to time-intensive studies and high network upgrade costs, which is a cost-allocation problem as much as a speed problem.
Richer markets split the same way between enabling conditions and delivery. The most detailed public comparison puts the UK at 82% for enabling conditions and 38% for deployment, which is why a headline rank is a poor guide to what a project team will actually face.
China's problem is different in kind: capacity is disclosed, but the rules for separating viable projects from speculative ones and for sharing upgrade costs are still administrative rather than published. Africa's constraint sits earlier in the chain, where the network does not reach the load at all. In smaller systems the same pattern repeats at distribution level: Caribbean rooftop solar capacity is roughly twice official tallies because so much of it is installed but never connected.
A U.S. developer faces a study queue; a Chinese developer faces an administrative gate; an African utility faces a missing network; a Caribbean rooftop owner faces a connection that never happens. One global target cannot see any of that, which is why the annex has to be built from operator-level data rather than a headline share.
The strongest objection is that 35x35 is a political instrument and should be judged as one. Its job is to move finance and keep grids visible. The Green Grids Initiative welcomed the target on roughly those grounds, crediting it with placing grids at the centre of the electrification agenda. On this account a queue baseline over-specifies a voluntary pledge, loads new reporting duties on statistical systems that are already thin, and duplicates work the IEA and national regulators do. The 2,500 GW figure, rough as it is, already tells the world where the blockage sits.
A sharper version comes from the countries the pledge is meant to help. Any indicator attached to a voluntary target can later be used as a test. The second global stocktake opens at this conference and is scheduled to conclude at COP33 in 2028, with technical work starting in mid-2027. A metric tabled now will be examined there, and negotiators have watched voluntary indicators turn into conditions on finance before.
The reply rests on the difference between a stock and a rate. A single global figure for queued capacity, however often it is repeated, cannot show whether projects are moving through the gate faster than last year, how many applications are abandoned, or who pays for the reinforcement that an interconnection triggers. A review scheduled for 2028 needs a rate. A template built from disclosures operators already make can standardize reporting without inventing new statistical obligations, and a clause stating plainly that the baseline cannot be used to condition finance answers the conditionality worry where it starts.
Three fields, published annually beside the pledge's progress report: queue length in projects and megawatts; withdrawal rates; and the allocation of upgrade costs. Two gaps would remain. Distributed solar, storage and demand response increasingly connect at the distribution level or behind the meter, and a template built only on transmission queues would describe a shrinking part of the system. A report can also stand in for a build: a ministry can publish a queue table and still appropriate nothing; pairing the queue data with the share of queued capacity holding a signed connection agreement or a committed upgrade budget makes that substitution harder to hide.
Revision is the third limit. The 21% and 23% starting points show how quickly definitions move, and any first edition will be corrected. The annex should publish a series with stated methodology changes rather than a single number, so that a revision reads as learning rather than failure.
For the presidency, the step is modest: attach the baseline as an annex, not a condition. Build it on existing operator disclosures and IEA compilation, cover queue length, withdrawal rates and cost allocation, publish it annually beside the pledge's progress report, and let the IEA or a designated secretariat hold the definitions. A first edition in 2027 would land before the stocktake's technical phase begins in the middle of that year, which gives the review a document to work from and gives investors a way to compare markets.
For project teams, the decision rule is different. If you are siting a plant or a data centre, queue length tells you how crowded the market is; withdrawal rate tells you whether the queue is clearing; cost allocation tells you whether the connection bill will kill the business case. Ask for all three before you commit capital. A 35% share in a communiqué is not a connection date.
Three recur. The first is treating a queue as a pipeline: a large queue is not a promise of future capacity, because most of it will withdraw. The second is comparing queue sizes across markets without adjusting for withdrawal rates and definitional differences — a 2,000 GW queue in one system is not equivalent to 2,000 GW in another. The third is reading a share as a connection: a country can hit 35% while its own projects wait, because the ratio can move on efficiency and fuel switching alone.
It is COP31's proposal, advanced by Turkey's presidency, to raise electricity to 35% of the world's final energy use by 2035. It is voluntary, not a treaty obligation, and it is measured as a share rather than a connection count.
Because a share is a ratio, not a flow. It can rise through efficiency gains, fuel switching or a redefinition of the denominator while connected capacity barely moves.
Globally, one analyst estimate puts it above 2,500 GW. In the U.S. alone, Berkeley Lab counted about 2,061 GW of generation and storage at the end of 2025. Both are stocks, not waiting times.
Queue length counts what is waiting; withdrawal rate counts what leaves. A long queue with heavy attrition may be clearing faster than a short, frozen one.
It depends on the market. Some allocate reinforcement costs to the connecting project, some socialize them, and the difference often decides whether a project proceeds.