A BAAJA Scorecard for U.S. Industry: Transmission Upside, Review Clocks and Where the Trade-Offs Land

Direct answer: the bipartisan permitting package known as BAAJA reads as climate-neutral in its worst case and climate-helpful in more optimistic macro scenarios, while its heaviest impact sits on the wires side — Rhodium Group modeling puts possible gains in yearly additions of new transmission capacity at 167% to 262% against the average pace of the past decade. For factories, warehouses, research campuses and e-commerce fulfillment sites, the real constraint stays the clock on environmental review and grid connection, not the language on the page.

That framing matters because load is climbing while conductors are not. The Energy Information Administration said in September 2026 that it expected U.S. electricity sales to reach 4,135 billion kilowatthours in 2026, up almost 2% from the prior year — growth that lands on a network whose expansion has stalled for years. This analysis therefore reads the same bill through five different yardsticks, compares the review clocks that actually set project calendars, and closes with role-by-role moves for operations, procurement and capital projects teams.

What did the first independent read of BAAJA conclude?

Conclusion first: no climate penalty, meaningful wires upside. Emily Pontecorvo and a colleague secured the earliest look at the Rhodium Group assessment of how the bipartisan permitting package would move emissions, and that reporting ran in Heatmap Daily at Heatmap.

The takeaway from that coverage is that the bill's most consequential clauses are likely neutral for climate change under a worst-case reading, and can support emissions reduction under more optimistic readings. Those readings turn on the surrounding energy economy — economic growth, oil prices and similar variables flowing back into the emissions arithmetic — rather than on how regulators interpret the statute.

The wires piece is the part that reaches an industrial balance sheet. Conductors are indispensable to decarbonization because usable wind and solar resources sit far from population and manufacturing centers; without new routes, that power cannot reach cities, towns and suburbs. BAAJA pushes on two levers at once: it affirmatively expands grid capability, and its revisions to environmental review law can shorten the path for power lines. Today, a federal environmental impact study for a transmission line consumes twice as long on average as the equivalent study for a pipeline, according to Rhodium data. On the strength of those two levers, the Rhodium analysis estimates the legislation could lift annual new transmission capacity additions nationwide by 167% to 262% relative to the past decade average.

How do the numbers compare? One bill, five yardsticks

Headline percentages are not interchangeable, and industrial planners routinely mis-read them by comparing a flow against a stock. Below, the same package measured five ways, with what each metric can and cannot support in a capital decision.

YardstickWho measured itWhat the figure saysDecision read for industry
Yearly new transmission capacity addedRhodium Group estimate for BAAJA167% to 262% above the past decade averageFlow metric, the fastest-moving number in the debate — and, as argued below, the likeliest undercount
Total transmission capacity in serviceResources for the Future sector modelingRoughly 30 percent more capacity of all types than its baseline by 2041, with interregional lines the largest shareStock metric; modest-looking because assets are counted at system scale and decades out
Miles of high-voltage line actually energizedBuildout tracking published in 2025; Rhodium Group also notes 2021-2024 as the four slowest construction years since at least 2010Only 322 miles of high-voltage line completed in 2024Denominator warning: a triple-digit percentage gain on a thin base still yields a small absolute mileage
Duration of federal environmental reviewRhodiumA line EIS takes twice as long as a pipeline EISThe reform targets the clock; it does not by itself deliver steel in the ground
Projects waiting to connectLawrence Berkeley National Laboratory, Queued Up tracker (2026 edition, data through 2025)About 8,200 projects actively seeking grid connectionQueue depth, not statute text, sets commissioning dates for on-site and off-site supply

Read together, the columns tell a coherent story: the reform's value shows up first in the rate of additions, later in system capacity, and only after hardware and land constraints are cleared. Rhodium Group's own research note is blunt about the starting point, describing the recent record on high-voltage construction as "abysmal" — a useful reminder that BAAJA is measured against a depressed baseline rather than a healthy one.

Why the transmission upside may be a floor rather than a ceiling

Conclusion: the 167% to 262% band probably understates the wires benefit, because the model behind it deliberately stops short of network physics. Rhodium's authors lacked time to run a full network study of the U.S. transmission system — the kind of work that would resolve the grid's physical footprint, actual power flows and pre-existing bottlenecks. They instead examined supply and demand inside the broader national energy system.

That was a defensible, and probably the only feasible, choice. Energy-system models at network resolution are expensive in calendar time, cash and compute: a more complete treatment could have taken weeks beyond the legislative window, let alone the modeling budget. The precedent is instructive. When the National Renewable Energy Lab examined how quickly Los Angeles could move to 100% renewable power earlier this decade, it modeled every transmission line and substation in LA; the supercomputer ran more than 100 million simulations, and the research effort consumed three years. Had Rhodium attempted even a fraction of that rigor on the national grid, its verdict would have landed after Congress had closed its voting window.

Where the undercount comes from (this is our analysis, not Rhodium's): network studies value congestion relief, loop-flow rerouting and the ability of a new line to unlock otherwise stranded renewable capacity. A supply-and-demand framing smooths those effects away, so a model that ignores bottlenecks tends to assign transmission less credit than operators see in practice. Two caveats for readers who want to cite this number in a board deck: the band is a range across scenarios, not a forecast; and it is expressed against the past decade average, so a rebound in raw mileage could narrow the apparent gap.

Where the bill touches industrial projects directly: connection in batches

Conclusion: the practical industrial prize is scheduling predictability, not a single permitting shortcut. One of the quieter ironies here is that exhaustive grid studies are already a routine compliance burden in the power sector. In much of the country, a proposed solar farm or battery installation cannot energize until operators assess how it affects congestion everywhere else — a serial review that is a leading reason new supply takes so long to hook up.

BAAJA aims to reorganize that process by letting plants join the grid in batches. That is not a new concept in regulatory design: under FERC Order 2023, effective November 2023, cluster studies replaced one-at-a-time serial analysis in many regions, with study windows designed in months rather than years and transitional RTO processes running somewhat longer. The comparison below sets the two regimes against each other.

DimensionSerial project-by-project reviewBatch or cluster review
Unit of studyOne project at a time; a neighbor's change can restart analysisA cohort studied together against a shared grid model
Schedule behaviorWaits cascade; Berkeley Lab's queue research has found the median interval from request to operation roughly doubled versus early-2000s cohortsRound-based calendars give a fixed planning horizon, assuming no re-scoping
Upgrade cost exposureEarly entrants absorb network upgrades that later entrants also benefit fromCosts spread across the cohort, with deposit and milestone requirements up front
Best fitLarge, one-off resources with bespoke engineering needsRooftop-plus-storage retrofits, campus microgrids, standardized utility-scale supply for a plant cluster
What industry gains—Commissioning windows that can be written into a plant launch plan

The trade-off deserves to be stated plainly: batching sacrifices project-specific granularity for throughput. A plant with unusual voltage or reliability requirements may still face individual engineering, and deposit-heavy milestone rules penalize speculative entries — which is exactly the outcome industrial buyers want when they compete for the same substation capacity as data-center developers.

What the reform does not fix: a risk register for planners

Four constraints sit outside the reach of any review-clock change, and each one can dominate a project schedule.

  • Hardware lead times. The ASCE infrastructure report card records that as of June 2024, procurement of new large transformers faced lead times of 80 to 210 weeks, up from roughly 50 weeks in 2021 — and about 70% of transmission lines were already 25 years or older. A faster EIS does not shorten a switchgear queue.
  • Case in point on elapsed time. The TransWest Express interregional project, a 732-mile line moving western wind toward load, received its federal notice to proceed on April 10, 2023 and began building in late 2023 — roughly 15 years after planning and permitting began, even after spells in a federal fast-track program.
  • Planning, siting and cost-allocation fragmentation. Analysts at Columbia's Center on Global Energy Policy describe the bill's transmission clauses as attacking three linked barriers at once: fragmented planning, state-by-state siting authority and unclear cost allocation. Repealing one does not repeal the others; implementation is where schedules are won or lost.
  • Rule-writing and pushback. BAAJA would codify the ban on federal rights of first refusal that FERC removed for regionally planned lines in its 2011 Order 1000, opening regional projects to competitive development. Public lobbying disclosures show incumbents pressing Congress to rewrite those clauses and restore their first-option status — a live source of schedule risk that no forecast captures.

Five misconceptions that misprice grid reform

  1. A triple-digit percentage gain equals a triple-digit mileage gain. Against a base of only 322 miles completed in 2024, the arithmetic of recovery looks very different in absolute terms.
  2. Permitting reform settles planning and cost allocation. Those are separate governance problems that survive the statute.
  3. Batching cancels congestion analysis. It reorganizes the same physics into cohorts; studies still happen, on a shared calendar.
  4. Climate-neutral means economically neutral. Reliability and wholesale price effects can justify the buildout even where emissions math is a wash.
  5. Transmission is a decarbonization-only story. Lines move cheap energy, absorb outages and reshape where industry can site power-hungry operations.

What should each industrial role do now?

RoleLikely mistakeRecommended move
Site and capacity expansion leadAssuming the bill shortens their own project's approval pathShortlist locations by substation headroom and cluster-study round dates obtained in writing, not by state goodwill
Energy procurementTreating power price risk as static through 2030Hedge congestion exposure with contracted supply or behind-the-meter generation where tariffs pass through constraint costs
Capital projects and supply chainBooking equipment after permit certaintyReserve transformer and HV switchgear slots 18 to 24 months ahead; lead times are the true critical path
Finance and investment analysisModeling a single-point capacity upliftRun a floor case at the smoothed-model result and an upside case reflecting network-study effects the model omits
Government and regulatory affairsEngaging once, at enactmentTrack rulemaking, interregional planning obligations and litigation over first-refusal language through implementation

Frequently asked questions

Is BAAJA a climate bill or an industrial-cost bill?

Both readings survive scrutiny. Its emissions effect looks neutral in a worst case and favorable in better macro scenarios, while its transmission provisions act on reliability, delivery of low-cost renewable power and, ultimately, electricity prices that manufacturers pay.

How much more transmission could the law actually produce?

The best-cited estimate puts yearly additions of new capacity 167% to 262% above the past decade average, while separate modeling sees roughly 30 percent more total capacity than baseline by 2041. The two figures measure different things and should never be averaged.

Why might that estimate be too low?

Because the study ran on supply and demand rather than a full network representation of the U.S. grid. Building that resolution is the work the National Renewable Energy Lab demonstrated for Los Angeles — more than 100 million simulations and three years — which was impossible inside the window Congress gave itself.

Is grid review slower than the legislative process it is meant to serve?

That is the irony the underlying reporting lands on: a level of study detail mandated for every new power plant is too slow to hand legislators an analysis before a vote. If Congress looks sluggish on infrastructure, the sector's own review machinery is the better benchmark.

What is the single most useful question a plant manager can ask this quarter?

Where our site sits in the next cluster-study round, and which network upgrades would we pay for if the round opened tomorrow. Those two answers convert a national debate into a project schedule.

Sources referenced

  • Rhodium Group, "Estimating the U.S. Energy System Impacts of the Bipartisan American Affordability and Jobs Act" — https://rhg.com/research/baaja-us-energy-system-impacts/
  • Resources for the Future, "Projected Effects of the Bipartisan American Affordability and Jobs Act on the Power Sector" — https://www.rff.org/publications/issue-briefs/projected-effects-of-the-bipartisan-american-affordability-and-jobs-act-on-the-power-sector/
  • Center on Global Energy Policy, Columbia, on what BAAJA means for the U.S. energy system — https://www.energypolicy.columbia.edu/publications/what-the-bipartisan-american-affordability-and-jobs-act-means-for-the-u-s-energy-system/
  • Lawrence Berkeley National Laboratory, "Queued Up" interconnection queue tracker — https://emp.lbl.gov/queues
  • FERC explainer on the interconnection final rule (Order 2023) — https://www.ferc.gov/explainer-interconnection-final-rule
  • ASCE 2025 Report Card for America's Infrastructure, Energy — https://infrastructurereportcard.org/cat-item/energy-infrastructure/
  • EIA press release of 9 September 2026 on record generation and electricity sales — https://www.eia.gov/pressroom/releases/press592.php
  • Utility Dive on the 15-year permitting path of TransWest Express — https://www.utilitydive.com/news/transwest-express-transmission-permitting-reform-brophy/650342/
  • American Clean Power / Council of Competitiveness tracking of high-voltage miles completed in 2024 — https://cleanenergygrid.org/new-report-reveals-u-s-transmission-buildout-lagging-far-behind-national-needs/
  • Heatmap Daily reporting on the Rhodium analysis — https://heatmap.news/daily/rhodium-transmission-benefits
Brand logo

Industrial Weekly

In-Depth Weekly Insights on Manufacturing & Supply Chain

AutomationSupply ChainSmart ManufacturingLogisticsEnergyGeneralGreen CarbonWorld

© 2026 Industrial Weekly.

Cookie Notice

We use cookies to improve your experience and analyze website traffic. Read our Privacy Policy to learn more.