Reuters reported on November 6, citing two people familiar with the plan, that YMTC (Yangtze Memory Technologies), China's largest NAND flash maker, wants at least 60% — with 70% as the stretch goal — of the equipment in its fourth Wuhan fab supplied by Chinese vendors, above the slightly more than 50% domestic ratio of its third fab. Construction is expected to begin in 2027, targeting NAND with more than 300 stacked layers for data centers. Read as a case study, this is a factory programme turning an externally imposed tool shortage into a repeatable qualification pipeline.
Conclusion first: the 60% figure is a procurement ambition attached to an unbuilt plant, not a signed capital plan. The fourth fab is expected to break ground in 2027 on the company's existing Wuhan site, where its headquarters sits. YMTC has opened preliminary discussions with some domestic equipment suppliers but has not issued formal purchase orders, so both the domestic share and the construction schedule can still move. The company declined to comment on the report.
That distinction matters for anyone building a project baseline. An engineering goal without purchase orders behaves differently from a booked capital plan: it signals direction to the supply base, gives vendors a design-in window, and preserves the owner's option to re-mix tools as qualification results arrive. The plan still carries two signals that industrial readers can act on — YMTC's own supply-chain localisation is accelerating, and Chinese equipment makers are being offered entry slots on an advanced memory line rather than only on mature ones.
Conclusion: the jump is the output of a forced re-specification, staged fab by fab, not a single procurement decision.
The transferable mechanism here is the "one fab per gate" structure: each new build raises the domestic ratio by a step, while the previous fab absorbs the yield risk. That is a scheduling trick plant engineers will recognise — you qualify on a line that is already running revenue product, then you scale on the next one.
Conclusion: layer count is how a NAND plant buys bit density without shrinking the cell, and the demand signal behind it is now unmistakably enterprise-grade.
Adding memory cells vertically increases how much data a unit of chip area can hold, so density rises with each stacking generation. High-capacity NAND of this kind is critical for data centres, AI servers and enterprise storage. As AI models scale, training data, model parameters and inference data all require large volumes of fast, high-capacity storage, which pushes enterprise NAND up the priority list inside server procurement.
Two verifiable market data points frame the case. TrendForce projected that NAND flash contract prices would rise 15% to 20% quarter over quarter in the fourth quarter of 2026 even as consumer demand stayed weak, driven by enterprise SSD orders; in its 1Q26 forecast the firm had already put NAND contract prices up 33% to 38%. In September 2026, TrendForce noted that U.S. cloud service providers had revised their enterprise SSD demand forecasts upward. If the fourth fab reaches volume production of more-than-300-layer parts, YMTC's technology position in the China market strengthens further — and, as Reuters observed, the target could put YMTC in a position to produce, inside China, more layers than some overseas competitors run locally.
Conclusion: the interesting gap is not between China and the world's leading edge, but between what Korean suppliers run at home and what they are allowed to install in their China plants.
| Manufacturer | Location | Layer trajectory | Constraint |
|---|---|---|---|
| Samsung Electronics | Xi'an, China | switching to 286-layer NAND flash | U.S. export controls bar some advanced manufacturing equipment from entering China; the two South Korean companies must obtain annual authorisation to bring U.S.-made tools into their Chinese plants, and the U.S. government has said it does not intend to approve exports that would let them expand capacity sharply or carry out major technology upgrades in China |
| SK hynix | Dalian, China | upgrading to more than 240 layers, up from the previous 192 layers | |
| SK hynix | Korea | 375-layer NAND validated, mass production targeted by end-2026 (reported) | Home-country roadmaps run roughly two generations ahead of their China fabs — the gap is regulatory, not technical |
| Kioxia / SanDisk; Samsung | Japan / Korea / U.S. | 332-layer BiCS10 with more than 37 Gbit/mm² bit density; 400-plus-layer wafer-bonded BV-NAND |
Source for the final two rows: Semiconductor Engineering's industry roundup (August 2026) and reporting carried by The Elec. For purchasing managers, the takeaway is that the China-based fabs of Samsung and SK hynix are effectively frozen mid-curve, which is precisely why YMTC's share gain is possible and why its equipment localisation is a capacity question as much as a technology question.
Conclusion: the new orders cluster in the "high-consumption, high-repeat" steps — clean, polish, etch — where domestic tools already run on YMTC's existing lines.
According to the people briefed on the plan, incremental domestic orders will concentrate in wafer cleaning, polishing and etch. These are indispensable baseline steps in NAND manufacturing, and Chinese vendors have accumulated substantial application experience on YMTC's current production lines; domestic suppliers already provide most of the cleaning and polishing tools the company needs, and have made progress on equipment for the deep vertical structures required by advanced NAND.
| Process step | Localisation status reported for YMTC lines | Vendors in play |
|---|---|---|
| Wet clean | Largely supplied domestically; high consumable volume after nearly every step | Cleaning specialists feeding YMTC fabs |
| CMP / polishing | Domestic 12-inch CMP tools widely adopted in Chinese advanced lines | Local CMP vendors |
| Etch (deep hole, stacking) | Bulk shipments into 232-layer-and-above lines; deeper aspect ratios are the frontier | NAURA and AMEC |
| Thin-film deposition | Growing share in memory lines | NAURA and AMEC plus deposition specialists |
| Lithography, inspection, complex steps | Still dependent on overseas suppliers | Western OEMs |
NAURA and AMEC are considered the likeliest beneficiaries of the incremental orders, given the breadth of their product portfolios and continued development of etch, deposition and related process tools. An outside read supports the pattern: the analysis accompanying Yole Group's Mainland China Semiconductor Equipment Industry 2026 report concludes that "Chinese companies have performed exceptionally well in the localisation of deposition, etch and clean, and CMP and thinning equipment" — which is why YMTC's ratio targets are being set step by step in exactly those clusters, not uniformly across the line.
Localisation is not independence. A 60% or even 70% tool bill still leaves the hardest steps — lithography, inspection and other complex processes — with overseas suppliers, because those tools demand extreme precision plus the stability and yield required for high-volume manufacturing of advanced memory chips. Being able to complete some steps with domestic tools does not mean foreign products can be replaced immediately across the board.
Misreadings worth flagging for any manager benchmarking this programme:
Conclusion: the reusable part is the staged-qualification project method, not the Chinese tools themselves.
Conclusion: YMTC is running two strategic tracks simultaneously — build fabs to expand NAND output, and raise the domestic equipment share to blunt foreign technology restrictions. The fourth fab is only part of the plan. Reuters reported in April this year that the company intends to build two additional plants in Wuhan, bringing the total number of fabs to five. Once the third, fourth and fifth fabs are fully operational, each is expected to process about 100,000 silicon wafers a month; the three plants combined would more than double YMTC's manufacturing capability against today's level. Industry reporting puts the company's two existing Wuhan fabs at roughly 200,000 wafers a month combined.
Market position is what underwrites that expansion. Data from research house Omdia show YMTC's share of China's NAND market reaching 38.5% in the second quarter of 2026, up from 28% in 2025, and surpassing Samsung Electronics to become the largest NAND supplier in the Chinese market. A separate capital signal: in August 2026 the Shanghai Stock Exchange accepted the STAR Market IPO application of the company's listing entity for a planned raise of RMB 33 billion, with proceeds earmarked for production-line upgrades and research and development, according to TechNode and Global Times reporting. For suppliers and customers alike, that is the financing arm of the same capacity plan.
The fourth fab remains at planning and supplier-negotiation stage. The actual mass-production timing of more-than-300-layer NAND, the realised domestic equipment ratio and final manufacturing yield all await verification. The significance goes beyond YMTC: Chinese semiconductor equipment makers previously won share mainly in mature nodes and some foundational manufacturing steps, whereas YMTC is trying to move more domestic tools onto an advanced 3D NAND line. If those tools run stably through high-volume production, they gain exactly the reference data the rest of the industry needs to enter applications with far higher technical barriers. If they do not, the fourth fab's ratio target becomes the first number to be revised.
At least 60% is the stated procurement goal, with 70% as the stretch target, versus slightly more than 50% at the third fab. Nothing is booked yet: no orders have been placed, so the final mix depends on qualification results.
Groundbreaking is expected in 2027 in Wuhan. YMTC's near-term capacity milestone is the third fab, now in equipment installation, reported to ramp to about 50,000 wafers a month in 2027.
Because export controls cap the Korean incumbents' China sites: Samsung Electronics is moving Xi'an to 286-layer NAND and SK hynix is taking Dalian above 240 layers from 192 layers, while both run higher nodes in South Korea. Producing more layers inside China narrows the local technology gap.
No. The company's own plan keeps lithography, inspection and other complex steps with overseas suppliers. The domestic gains are concentrated in clean, polish, etch and deposition.
More bit supply and, for enterprise SSD procurement, an additional qualified source. Near-term pricing is still set by AI and data-centre demand — TrendForce forecast NAND contract prices up 15% to 20% quarter over quarter for the fourth quarter of 2026.