A reservation signed in a boardroom reaches the shop floor years later, as tool moves, cleanroom staffing and shipment schedules. That lag is the right lens for the manufacturing plan NVIDIA assembled with its supply chain partners: substrate output is set to grow 2.5x, semiconductor testing throughput is set to double from 2026 to 2027, and nearly every milestone in between already carries a date.
The trigger is demand for accelerated computing and a full-stack AI factory platform rather than one product line. By working with Amkor Technology, IBIDEN, King Yuan Electronics (KYEC), Samsung Electro-Mechanics, Siliconware Precision Industries (SPIL) and Unimicron Technology Corporation, NVIDIA is pushing capability outward into substrates, advanced packaging, testing and optical engines at new and existing suppliers — a move aimed at resiliency and redundancy across four process layers that rarely fail alone.
| Capacity layer | Target stated in the plan | Where it lands | Dated milestone |
|---|---|---|---|
| Package substrates | grow 2.5x over the next three years | Japan, South Korea, Taiwan | additional capacity begins ramping in the first quarter of 2028 |
| Advanced packaging (interposer wafers) | greater than 300% increase | South Korea | by end of 2028 |
| Semiconductor testing | total capacity to double from calendar 2026 to 2027 | US, Taiwan, Singapore | April 2027 and February 2027 for high-volume production |
| Optical engines for co-packaged optics | 15x, then another doubling | Taiwan | mid-2027, then the end of 2028 |
Read together, the four lines describe a chain being widened at every handoff, not simply one bottleneck being relieved.
Under the agreement signed and announced earlier this year by IBIDEN, NVIDIA is extending a multibillion-dollar capacity reservation advance behind the Ono Plant expansion in Japan. That site is pointed at capacity reaching 3x current levels, with additional capacity expected to begin ramping in the first quarter of 2028.
South Korea's existing operations contribute immediate capacity into the substrate supply chain, while facility upgrades and new factories in Sejong and Busan follow. By 2028, production allocated to NVIDIA is projected to represent a significant portion of Samsung Electro-Mechanics' total annual package substrate production capacity.
A capacity reservation agreement backs Unimicron in its KF substrate manufacturing expansion in Taiwan. That expansion is expected to begin adding capacity in the second quarter of 2027 and to reach full capacity by mid-2028 — a two-step curve buyers can plan around.
NVIDIA and Amkor intend to expand advanced packaging capacity in South Korea, targeting a greater than 300% increase in interposer wafer capacity by the end of 2028. The planned expansion, alongside Amkor's development of new manufacturing facilities there, supports higher production volumes for current and next-generation platforms.
Total semiconductor testing capacity is expected to double from calendar 2026 to 2027, with buildouts in the U.S., Taiwan and Singapore providing support. The $1.1 billion capacity reservation advance to King Yuan Electronics (KYEC) funds new U.S. testing facilities and equipment, with high-volume production targeted for April 2027. Expanded testing operations in Singapore are expected to reach high-volume production in February 2027. The effort also strengthens US manufacturing.
Siliconware Precision Industries (SPIL) is working with NVIDIA to expand capacity in Taiwan for optical engines used in co-packaged optics, addressing the connectivity requirements of large-scale computing infrastructure. The target is an increase of 15x by mid-2027, with aims for another doubling by the end of 2028.
No. It is a capacity-reservation program layered onto supplier sites: output from existing operations plus facility upgrades and new factories, ramping on staggered dates instead of one opening.
Optical engines for co-packaged optics, at 15x by mid-2027, with aims for another doubling by the end of 2028.
Substrates at IBIDEN's Ono Plant in Japan, at Samsung Electro-Mechanics sites in Sejong and Busan, and on Unimicron's KF expansion in Taiwan; advanced packaging in South Korea; testing in the U.S., Taiwan and Singapore.
The substrate line: 2.5x over the next three years, with Unimicron reaching full capacity by mid-2028 and IBIDEN's new capacity ramping from the first quarter of 2028.
Because the plan consumes equipment, cleanroom space and test throughput — inputs that feed availability, pricing and lead times for anyone deploying automation, plant electrification or edge compute hardware.
The most useful element here is not a percentage; it is a calendar. Each target now has a site, a partner and a quarter attached, which means slippage will surface as moved dates rather than softened language. Tracking the substrate, packaging, test and optics programs through 2028 is the practical way to see when reservation language becomes delivery performance.