NIO has not abandoned its large-format cylindrical battery ambition; it has changed where the manufacturing risk sits. Reporting by Jipian Lab indicates that the automaker’s self-designed large cylindrical cell will move toward line validation through contract manufacturing, with EVE Energy and Gotion High-tech positioned to advance a very small batch of cells around year-end.
For WorldIndustrialWeekly readers, the story is less about a single vehicle launch and more about how industrial firms sequence capital, capability, and production partners. The company had previously signaled an in-house route for battery work, then moved toward a partner-based production test. The key operational question is whether the cell can be made at small batch without assuming the entire market has shifted away from prismatic batteries.
The published record can be read as a compressed manufacturing timeline. The earliest milestone was in 2021, when NIO formed a battery R&D team. In 2022, Li Bin said the company had assembled a team of more than 400 people and planned to introduce an 800V high-voltage platform battery pack in 2024, a plan commonly associated with 4680-format cells.
The capital plan followed. In February 2023, NIO announced the start of phase I of its Hefei industrial base, with planned capacity of 40GWh. The article also notes that funding pressure led to the 40GWh production-line equipment purchase being placed on hold six months later.
At the end of 2023, at NIO Day, NIO disclosed an in-house 46105 large-cylindrical solution paired with a 900V high-voltage platform. The announced parameters were a cell energy density of 292Wh/kg, a whole pack capacity of 120kWh, and 5C fast-charging support. The original plan pointed to ET9 as the target application, but ET9 reached launch with a CATL prismatic battery pack instead.
By September this year, Li Bin described cumulative battery R&D spending as more than 2 billion yuan, said the main development line remains a large-cylindrical long-life cell, and explained the operating model as in-house design plus contract manufacturing. The most recent step in the reported plan is the year-end trial output from EVE Energy and Gotion High-tech.
| Element | Reported value | Why it matters to operations |
| Team formation | 2021; more than 400 people reported in 2022 | Shows the cell effort had an organizational base before production choices were made. |
| Platform plan | 800V in 2024; 4680 association | Indicates the intended vehicle architecture, not a finished cell output plan. |
| Capacity plan | February 2023 Hefei industrial base phase I; 40GWh | Shows scale ambition that later faced capital constraints. |
| Capital pause | 40GWh equipment purchase put on hold six months later | Explains why partner manufacturing can reduce near-term capital intensity. |
| Cell announcement | End of 2023 NIO Day; 46105; 900V; 292Wh/kg; 120kWh; 5C | Defines the technical target disclosed by NIO. |
| Product reality | ET9 launched with CATL prismatic pack | Shows target plan and shipped configuration can diverge. |
| Investment and model | September this year; more than 2 billion yuan; in-house design plus contract manufacturing | Frames the current path as technology ownership with outsourced production. |
| Immediate step | year-end small batch by EVE Energy and Gotion High-tech | A production milestone, not proof of mass-market adoption. |
The report’s explanation for EVE Energy is straightforward: it is described as a BMW large-cylindrical battery supplier and the partner with the broadest experience in mass-producing large cylindrical cells. Gotion High-tech is described as a Hefei enterprise active in the large-cylindrical field, giving it higher fit with the project’s location and supply-chain context.
From an industrial perspective, these two profiles serve different functions. One brings process experience at the specific format; the other brings geographic and supply-network proximity. A small batch can test whether both are needed, or whether one route can carry the line while the other validates second-source capacity.
The article also notes that large cylindrical remains a minority format. Outside Tesla and BMW, few installed vehicle models use it, and prismatic batteries remain the absolute mainstream. That distinction is important: a partner-made large cylindrical cell should be read as an engineering and supply-chain experiment, not as evidence that the mainstream industry has already re-tooled.
| Misunderstanding | What the reported facts actually support |
| Year-end small batch means mass production has started. | The reporting says a very small batch is expected at year-end, which is closer to line validation than volume supply. |
| Contract manufacturing means NIO has stopped developing the technology. | The reported model is in-house design plus contract manufacturing, with R&D spend described as more than 2 billion yuan. |
| The 46105, 900V, 292Wh/kg, 120kWh, and 5C figures guarantee vehicle deployment. | Those figures were disclosed at NIO Day, while ET9 launched with a CATL prismatic pack. |
| Large cylindrical is replacing prismatic batteries. | The report says prismatic batteries remain the absolute mainstream, and large cylindrical is still niche outside Tesla and BMW. |
| Partner choice proves final supply is locked. | The immediate milestone is small batch output by EVE Energy and Gotion High-tech, a test that can reveal whether the partners can support the design. |
According to the reporting, the outsourced part is production of a NIO self-designed large cylindrical cell. EVE Energy and Gotion High-tech are named as contract manufacturing partners expected to move a very small batch toward line output around year-end.
The reported sequence includes formation of a battery R&D team in 2021, a team of more than 400 people and an 800V platform plan associated with 4680 in 2022, then an end-of-2023 NIO Day disclosure of a 46105 large-cylindrical solution for a 900V platform with 292Wh/kg cell energy density, 120kWh pack capacity, and 5C fast-charging support.
The article says NIO announced phase I of its Hefei industrial base in February 2023 with planned capacity of 40GWh, then put the 40GWh production-line equipment purchase on hold six months later because of funding pressure.
It shows that a disclosed cell plan and a shipped vehicle configuration can differ. The original target application was ET9, but ET9 reached launch with a CATL prismatic battery pack.
The reported view is that prismatic batteries remain the absolute mainstream, while large cylindrical is still a niche format with limited installed-vehicle use beyond Tesla and BMW.
The practical takeaway for WorldIndustrialWeekly’s industrial audience is a separation of layers: design ambition, capital scale, partner capability, vehicle packaging, and market format are not the same signal. The next useful checkpoint is not a single announcement, but whether the year-end small batch can be repeated with the stability that a supplier network can rely on before large cylindrical is treated as anything more than a controlled pilot.