Two gas machines on the same US grid averaged 58.8 percent and 14.1 percent of their nameplate output in 2024 (US Energy Information Administration, EIA, capacity-factor data). Megawatts describe scale; they do not describe hours. That gap is why emissions lock-in accounting — a lifetime carbon promise built from operating profile, fuel contracts, co-firing supply, retirement dates and displaced capacity — is a better review test than a capacity filing, and why it fails the moment it assumes full output or becomes a blanket veto.
I read these files the way I read a line-side report: the machine name tells you nothing, the running hours tell you everything. A lifetime screen earns its place in project review when it forces those hours onto paper before contracts harden.
It measures an obligation, not an object. The IPCC Working Group III (WG III) Summary for Policymakers states, with high confidence, that continued installation of unabated fossil fuel infrastructure will lock in emissions. The WG III Chapter 2 describes accounting studies that begin with plant-level data for existing fossil fuel infrastructure and then assess future carbon dioxide (CO2) emissions. Applying that logic to new projects does not need new physics; it asks what existing methods already do: move from an installed object to a future obligation.
The World Resources Institute defines carbon lock-in as fossil-intensive systems that perpetuate, delay or prevent transition. The Stockholm Environment Institute adds that supply-side fossil infrastructure can deepen the same effect. The Energy for Growth brief separates the two ideas operators most often confuse: lock-in is path dependency, stranded assets are a possible later financial consequence. Those descriptions point to a governance task — the approval file should show commitments that are hard to unwind.
The peer-reviewed starting point is explicit about uncertainty. Tong and colleagues in Nature (2019) estimated that fossil infrastructure existing in 2018 would emit about 658 billion tonnes of CO2 over its assumed life, with a range of 226 to 1,479 billion tonnes, and that planned plants would add roughly 188 billion tonnes (37 to 427), about 846 billion tonnes together, with more than half from power. Those ranges are wide because lifetime and utilisation assumptions are wide. That is the number a screen must shrink with project evidence, not with a default.
Because capacity answers "how big" and never answers "how long, how often, or instead of what". Public research around the 2021 report on global energy infrastructure gives the scale: coverage by IESPlaza and the Quark encyclopedia entry says the effort tracked more than 100,000 energy infrastructure assets in power, steel, cement and land transport, sectors that emitted 24.1 billion tonnes of CO2 in 2020, about 70 percent of global carbon emissions, and describes about 480 billion tonnes of locked emissions from infrastructure expected to operate over coming decades, with a typical service life around 40 years.
Those figures work better as a diagnostic than as a project score. They cover several sectors and global aggregates. The structural lesson stands: if power, steel and cement assets last around four decades, an approval is far from a one-year emissions event. The same coverage says emerging economies carry much of the demand for new capacity because infrastructure gaps and needs remain concentrated there — a fact that should temper any screening rule.
| Screen | What it counts | What it hides | Use it when |
|---|---|---|---|
| Nameplate capacity filing | Physical scale: megawatts, tonnes, barrels, cubic metres | Operating hours, fuel terms, retirement date | Resource adequacy arithmetic only |
| Lifetime emissions range | Commitment across likely service life under stated assumptions | Why the region wants the asset and what it displaces | Before contracts and construction become irreversible |
| Flexibility audit | Cycling depth, ramp rate, start time, hours needed for balancing | Total lifetime tonnes if run as baseload | Peakers and reserve units built for renewable gaps |
| Displacement ledger | Which older unit retires, when, and by what permit line | Emissions outside the fence: transport, ports, feedstock | Modernisation claims in cement, steel and heat |
| Grid connection status | Queued capacity, commissioned lines, storage under contract | Behind-the-meter fuel already burning | Any project citing grid timelines as a reason |
No single row is the verdict. A capacity filing tells you whether a service is covered; a lifetime range tells you what that coverage costs over 40 years; a flexibility audit tells you whether the machine can be run the way the promise assumes. I have argued the flexibility case separately at no new unit should count toward resource adequacy until it passes a flexibility audit.
A usable method asks for hard inputs before contracts and construction become irreversible. A gas turbine on a crowded grid and a gas turbine behind a data centre that must keep servers alive can carry very different emissions paths; a cement kiln tied to coal contracts and a kiln certified for alternative fuels diverge long after approval.
In the parts of the file nobody files. The Sina Finance energy analysis says hyperscale cloud providers and wholesale compute clusters could take 70 percent of global IT load, and that under a 60 percent average load assumption, projected data-center operating emissions reach 436 million tonnes of CO2 in 2031, above United Kingdom 2025 annual emissions; it also says some computing projects rely on gas units behind the meter because grid connection timelines are long. Independent reporting matches the mechanism: Enverus describes grid interconnection waits stretching to five years, and Power Engineering reports that 22.5 gigawatts of behind-the-meter capacity is tied to new data centres targeting operation by 2030, the shift driven predominantly by connection queues. The Lawrence Berkeley National Laboratory queue tracker counts about 8,200 US projects and 1,312 GW of generation seeking interconnection at the end of 2025.
If renewable procurement promises are checked and the gas units beside them are ignored, an accounting system misses a lock-in route that is becoming common. The commercial half of that risk — who pays when electricity access becomes a barrier to compute growth — is the question I would ask alongside the carbon line in who absorbs the cost of AI electricity shortages.
Three failure modes recur, and each has a counter-evidence line.
The most serious objection is real, not rhetorical. A rigid carbon budget for every fossil asset would penalise projects in regions that still lack reliable power, hospitals, schools, transport and heat inputs. It could make energy security more expensive, and it could give lenders and governments a convenient reason to delay modest-emissions assets while saying nothing about credible replacement projects. In its hardest form, the method turns climate measurement into an excuse to stop investment without showing who would supply the same service.
The disagreement between credible sources shows why the screen must stay comparative. Climate Action Tracker says short-term energy security responses must not undermine long-term climate goals, while recognising that governments face real constraints. Greenpeace Southeast Asia argues that growing Asian energy needs cannot justify new fossil gas expansion, and its Gastech position connects gas deals to long asset lives. One side is worried about present deprivation and continuity of output; the other is worried about a future that becomes harder to clean. The Tsinghua report coverage cited alongside the 2021 infrastructure data offers the bridge: lock-in can be reduced by shorter service lives and lower utilisation.
A practical approval document could ask for a plant-specific lifetime emissions range, planned operating hours, fuel contracts, co-firing supply assumptions, decommissioning commitments, displacement of older capacity, and a review date before those commitments expire. Where a plant sits inside a supply chain that extends beyond its fence, the file should show transport, storage, pipeline use, sourcing or port capacity. Self-reported transition plans can be optimistic, so independent checks carry the credibility: grid forecasts, fuel delivery records, equipment specifications, permits and retirement filings.
Run this as a four-step framework on any asset you are asked to approve, and it transfers across power, steel, cement and transport-linked projects: first, baseline the promise — state a range from hours and fuel terms, never from nameplate; second, name the replacement — record which older or dirtier unit retires, by which date and under which filing; third, price the flexibility — show what storage, transmission, demand response or fuel conversion would do to the range; fourth, set the review date — a fixed point before contracts harden, with the disclosure of who supplies the same service if the project does not proceed. Fossil projects already require environmental review. The open question is whether reviewers ask about future emissions with the same seriousness they ask about air quality, water use and land permits.
No. It is a comparative screen. It becomes wrong when used as an all-or-nothing veto that blocks assets without showing what would serve the same demand. Supportable use is disclosure and testing before investment becomes locked.
Because capacity and commitment diverge by multiples, not margins: the same fuel produced average utilisation of 58.8 percent for combined-cycle gas and 14.1 percent for simple-cycle gas turbines in the EIA 2024 data, and a typical asset in these sectors serves about 40 years.
A single lifetime number that assumes decades of full output, ignores displacement of dirtier capacity, treats co-firing as a slide, and names no retirement date. Each of those four assumptions can be requested in writing.
Tong et al., Committed emissions from existing energy infrastructure jeopardize 1.5 °C climate target, Nature (2019)
IPCC WGIII Summary for Policymakers headline statements
IPCC AR6 WGIII Chapter 2 emissions trends and drivers
World Resources Institute carbon lock-in definition
Stockholm Environment Institute carbon lock-in from fossil fuel supply infrastructure
Energy for Growth untangling stranded assets and carbon lock-in
IESPlaza report coverage on global energy infrastructure lock-in
Quark encyclopedia entry on global energy infrastructure carbon emissions and lock-in effect
Sina Finance AI energy and data center emissions analysis
US EIA average capacity factors by source, 2024 (Statista compilation)
Enverus, grid interconnection waits and behind-the-meter gas
Power Engineering, data centres skipping the grid queue (22.5 GW behind-the-meter)
Lawrence Berkeley National Laboratory, Queued Up interconnection tracker
IEA World Energy Outlook 2025, Stated Policies Scenario
Carbon Brief, IEA fossil-fuel demand peak analysis
S&P Global, US EIA coal capacity outlook
IEEFA, US coal capacity and generation decline
Climate Action Tracker fossil fuel phase-out assessment
Greenpeace Southeast Asia Gastech 2026 press position