Short answer: the bill compresses approval time, not physics. A bipartisan permitting reform package cleared a key procedural hurdle last night, when more than 70 senators — Seventy-three in all — voted to advance it. It would create a one-stop federal approval path for large transmission lines, stop data-center developers from exporting grid costs onto customers, and shorten the gap between “approved” and “energized”. It does not fund plants, hire crews or guarantee power-line routes.
Start where the story actually lands on a shop floor. In the PJM Interconnection, the regional transmission organization that runs the wholesale market across parts of 13 states, capacity prices moved from $28.92 per megawatt-day for the 2024/25 delivery year to $329.17/MW-day for 2026/27 — more than eleven times, according to the Institute for Energy Economics and Financial Analysis (IEEFA). That line item is a factory input cost, not a lobbying issue. A Senate vote on paper now decides how fast that curve stops bending.
Seventy-three votes is a working majority signal, not a symbolic one. “Seventy-three is a great number,” Senator Martin Heinrich of New Mexico, one of the bill’s Democratic coauthors, told me about 12 hours later at a Heatmap breakfast in Washington, D.C., where we returned to permitting and power lines. “It suggests we’re on track to get this done. And I think we just need to be patient and let the process play out.”
Heinrich and I have spoken repeatedly about transmission over the past year. Topics that were niche 18 months ago — whether a president can revoke a project’s permits, who pays for a hyperscaler’s load — are now open arguments inside environmental groups, the clean-energy supply chain and liberal lawmakers. He sits near a win: a bill that puts transmission lines, which carry zero-carbon power, closer to the fast-track federal footing that natural gas pipelines already hold. His framing was a question rather than a pitch: how can the political class deliver on affordability, and how can the United States compete in the world, when the gap between asking and building is measured in decades.
Asked what the biggest whip victory was for him or Senator Whitehouse before the count, Heinrich answered with the arithmetic. When a vote hits above 70, he said, the caucus is taking the work very seriously; after a caucus meeting over the weekend and then last night’s roll call, there is an implicit trust in a number over 70. “My goal here is to take the politics out of permitting,” he said. “If you’ve done everything right — and you get your final permit to actually construct — you should be able to take that to the bank.”
What worried him was not the tally but the two channels of politics running through it: substantive bargaining between House and Senate members, which he called healthy and rare in recent years, and an online, hair-on-fire stream that he said makes him worry about democracy as a whole. The gap between those channels is where a project plan gets mispriced. Heinrich recalled a 23-year-old graduate student in New Mexico who knows his record well, and said seeing protests on that campus, or on an Albuquerque overpass, is far removed from what the legislation tries to do. “People want to get to yes,” he said, adding that this election “is not a mandate but a job interview.”
Between five years and fifteen, depending on which permit you are waiting for. Heinrich said today it takes two decades to build a really important interregional transmission line, and that the bill would still leave five years — better for competitiveness against China and other near-peer competitors, “but not a magic wand,” because environmental impact statements still take years.
Independent timing data matches his framing. For transmission projects that completed an environmental impact statement (EIS) between 2010 and 2020, review under the National Environmental Policy Act (NEPA) alone averaged 4.3 years, according to the Bipartisan Policy Center. The Rhodium Group found that 2021–2024 were the four slowest years for high-voltage transmission construction since at least 2010 — the constraint is process and labor, not towers and conductor.
SunZia is Heinrich’s own reference case, and it is the right case for anyone who builds to schedule. He called it one of the best projects he has ever worked on: 3.6 gigawatts of clean power, serious mitigation, land bought for its environmental value in New Mexico, and stakeholder engagement as good as any developer he has seen. It still took 17 years to permit. “Seventeen to 18 years is nuts,” he said; lawmakers cannot iterate on that timescale. The project needed two records of decision, and John Podesta, returning to the Biden administration, told him: “Didn’t we do this? I thought we already did this.” Project filings describe SunZia as a roughly 550-mile, ±525-kilovolt high-voltage direct current line developed by Pattern Energy; labor is being contracted in the same corridor, with the International Brotherhood of Electrical Workers (IBEW) announcing in December 2023 a $1.3 billion project-labor agreement for a 580-mile line across New Mexico and Arizona.
Use the cheapest credible number, not the biggest one. Heinrich said outside assessments range from grid cost savings in hundreds of billions to single-digit percentage reductions of power bills in a decade or so, and he argued the bill would pay even if it delivered only the data-center provision — “if all the bill transferred $35 billion from data center developers into consumers’ pockets, I would be enthusiastic.” He blamed some utilities for passing those costs to customers, called that outrageous, and said rate-basing something does not mean it should be rate based.
Our desk's read of the electricity and transmission rewrite pointed the same way: the real value is in who pays for firm capacity. Where the published estimates land:
| Estimate | Source | How to use it |
|---|---|---|
| Electricity prices 0.5–1.0 cents/kWh lower in real terms; 3–5% below reference prices | Rhodium Group, 3 Nov 2026 | Model this as the mid-case for an energy budget, not a guarantee |
| “Modest power sector benefits”; gains larger with stronger complementary policy | NRDC initial assessment, 26 Oct 2026 | Treat as downside discipline on permitting-only savings |
| PJM wholesale costs up 46% to $56.7 billion so far this year, with data-center load about 9% of it | Utility Dive analysis, Aug 2026 | Explains why ratepayer-protection language is the bill’s loudest shop-floor clause |
| $35 billion cost transfer from developers; hundreds of billions of grid savings claimed | Heinrich, and outside estimates he cited | Use his floor number, not his ceiling number, in a five-year plan |
Heinrich’s broader claim is that grid planning has already changed shape. He grew up around a kitchen table with an IBEW dad, in a system where a dam or a coal plant pushed power across big wires, then small wires, then to homes and factories. The bill leans toward a two-way grid, and he said he has not yet got the public to look at the geothermal leasing changes, distributed energy resources (DER) or the item that excites him most.
Because a contracted megawatt you never generate still has value. Heinrich said he hates the term virtual power plant (VPP) because “they are not virtual; they are real”: if you have a gigawatt and can contract for it to appear when needed — by dimming half the lights in a Walmart or drawing on batteries in electric vehicles — that is real power with enormous grid value. He said utility culture is conservative, that this is demonstrable technology, and that if the bill passes, utilities will be able to respond to wholesale markets and cannot be blocked. For a plant that already runs demand response, that is a balance-sheet item, not a pilot.
Nothing that makes off-grid gas cheap. Asked whether the ratepayer protections would push data centers toward behind-the-meter gas, Heinrich said he does not know a single hyperscaler saying that, despite many conversations about off-grid generation. He called it far more expensive and difficult to operate and maintain, said it is insane to build a data center not connected to the grid, and dismissed repurposing airplane engines to run them as “nuts”, challenging fans to carry the maintenance cost because, he said, it is going to fail. His argument for grid connection is arithmetic: customers do not pay the full freight of the worst day of the year spread across every other day. “That is why the grid exists,” he said. He does not see offsite generation as a viable business plan for anyone.
Yes for the construction permit, no for everything before it — and that asymmetry is the whole point of the bill. I noted that permitting certainty has been the loudest argument for it, including stopping a future president from doing what Trump has done to wind energy. Heinrich said no, it cuts both ways: a real gain depending on which side of the transaction you sit, and some people in the environmental space would rather keep the ping-pong between Trump and Biden running. Quoted criticism of Podesta’s reading — that the bill would let a president keep a permit granted illegally — drew a flat no. Fidelity to the underlying statute still governs; violate the Mineral Leasing Act or another permitting law and you create real jeopardy. Anything up to the final permit can be overturned, and a lease issued along the way can be reversed by the next administration.
Businesses should read that as a litigation deadline. If your model is suing projects, Heinrich said, it gets harder: you can still litigate, but you cannot wait six years to do it.
That is the most under-priced risk. Heinrich answered with an institutional argument: the more Congress asserts its mandate through legislation, the more power shifts away from the Supreme Court and the judiciary; when Congress cannot act, power moves to the courts and the administration, which he called bad for democracy, for America and for building things. The goal, he said, is to get good projects to yes and to fail bad ones fast, not to greenlight bad projects but to put them in the right places.
The criticism he accepted came from me, quoting it back: “Look, it’s a big bill. It’s 400-something pages. It makes changes to NEPA and the National Historic Preservation Act. It makes changes to the Clean Water Act. The Supreme Court is controlled by conservatives at the moment, and they have been willing to improvise with big new doctrines such as the major questions doctrine. How can we be sure — and how can you be sure — that you’re not writing traps into these laws that courts will come along and use in the future?” He added the narrower fear in one line: “Look at this recent and specific law, it lets presidents do X.”
On the hardest version of that charge — “Look, if we do this now, then the president gets two years to build whatever he wants, and that includes ICE detention centers.” — Heinrich said the drafters walked through case law in places like New Jersey to ensure the bill does not facilitate it, and that a major project takes years, so it would not measurably change what this president can accomplish. He repeated the timing math: two decades now, five years after.
Because waiting has a 20-year track record. Senator Merkley voted no yesterday and said the bill should be picked up next year in the new Congress, and other colleagues urged waiting until January. Heinrich asked how many times that has worked: he has watched the pattern since arriving in 2008 — almost 20 years — and said lawmakers should do far more next session, but this bill should become the floor, then the floor gets raised everywhere possible. The other reason is procedural: the amendment process is usually negotiated between the majority and minority leaders, and the Senate’s drift away from amendments, he said, has not served legislation well.
We have already examined how the midterm result complicates the package's path in the lame-duck session; Heinrich's answer here turns on the same variable. He said the alignment of House, Senate and White House has real value in making energy cheaper and putting more clean power online — and that he takes a win with the president wherever he can get one, because it is fleeting and he is what he is. He said the president did not help last night: “His phone blew up, and the White House was like, ‘Sorry, he just says stuff.’” Asked whether the president has to approve projects for the bill to make sense, he said no, because the greatest value is for the next president.
On legacy, he pointed at the Biden administration: the Bipartisan Infrastructure Law and the Inflation Reduction Act were huge lifts, yet the president could not deliver within a time frame Americans would appreciate because permitting was a 10-year-plus regime, even with money and the Department of Energy and Department of Interior lined up. He said he will do everything in his power to make sure the next president is a Democrat, but that whoever it is still has to govern and compete with the rest of the world, so the value of the bill is really for the country. He added that dozens of stalled projects are being approved now, which has value today.
A level playing field, not a new subsidy. Almost all incoming Democrats — including, he said, certainly in the Senate — have pledged to restore wind and solar tax credits. Heinrich asked a budgeting question instead: the credits are gone now and there are still tons of viable wind and solar projects, which suggests the money may be more valuable somewhere else. Generation is being decarbonized with wind, solar and batteries; transport and the process industries, which run on chemical processes, are not. His position is that wind and solar move faster if government gets out of the way.
His home state sets the frame. New Mexico is in the climate normal he did not think he would see in his lifetime: the driest it has been in 1,200 years, and, once El Niño kicked in, floods in recorded history in the last month. “That is what their grandkids will know for their entire lives,” he said — so solve it with the most effective approach and invest where the difference is biggest.
Treat permitting as a schedule input and run the same four steps whatever the Senate does next.
Copyable framework: one permit path, one payment rule, one deadline. Any site expansion or load decision that can be reduced to those three lines will survive whichever administration holds the pen.
No. Published estimates range from a 3–5% real price reduction (Rhodium Group) to “modest benefits” (NRDC). Heinrich’s own floor is the $35 billion cost transfer from developers.
Partially. Heinrich puts an interregional line at two decades today and five years after the bill — still longer than most equipment cycles.
Heinrich says no, provided the law was followed; anything before the final permit, including an interim lease, can still be reversed.
Not on cost. The bill’s logic runs the other way: keep load on the grid and make large developers pay their own freight.
Text. A 400-something page rewrite of NEPA, the National Historic Preservation Act and the Clean Water Act will be read by courts for decades.