COP31's Nuclear Momentum Needs a Construction-Cost Overrun Registry

A public registry of construction cost and schedule deviations, covering large reactors and small modular designs, is the most useful thing the nuclear industry could put in front of COP31 delegates. The summit has moved the argument from whether reactors should be built to whether they can be finished on budget, and the second question can only be settled with a record. The registry earns its place under conditions. It has to cover every generation technology, its figures have to be checked by someone other than the companies reporting them, and first-of-a-kind units have to be published on a lag. Built as a nuclear-only scoreboard, or published in a way that raises the cost of capital for the first units and cancels the orders that would produce the learning, it would make the problem it is meant to expose worse, and the case for it would collapse.

Thirty-five percent by 2035 turns the nuclear argument into a delivery test

COP31 opened this morning in Antalya, and the host country's main proposal is the 35x35 pledge: electrify 35% of the world's final energy use by 2035. Electricity carries 21% of end-use energy today, and the Rhodium Group projects 28% by 2035. Closing the remaining gap means building at a rate the power sector has not managed for decades, and it means the plants that get ordered actually get finished.

Nuclear has a place in that build-out. The IEA's executive director, Fatih Birol, said in March that about 70 GW of nuclear capacity was under construction worldwide, the highest figure in 40 years. The grid is a parallel constraint. The IEA estimates that annual grid investment of roughly $400 billion needs to rise by about 50% by 2030 to carry the electricity a higher-reliability system would produce, and it puts the total net-zero energy infrastructure bill to 2050 above $100 trillion. Every dollar of that has an alternative use. Anthropic's $3.4 billion agreement for 1.7 GW of gas-fired engines went to equipment that can be delivered faster than a reactor can be licensed.

The timing problem is sharper than the general cost problem. The IEA expects data centre electricity demand to double by 2030, and reactors ordered now would not be running by then. Recent projects in the United Kingdom, France and Finland have all run past their budgets and their schedules. If nuclear is part of the answer to 35x35, the industry has to be able to show which projects went wrong, by how much, and why.

The overrun record is where the credibility claim is weakest

The Boston University Global Sustainability Institute study of 662 energy infrastructure projects in 83 countries, spanning 1936 to 2024 and $1.358 trillion of investment, found that more than 60% exceeded their planned construction cost. Nuclear was the worst category on the authors' own measure. The average plant overran by 102.5%, ending up $1.56 billion above its expected cost. Hydropower averaged 36.7%, geothermal 20.7%, carbon capture and storage 14.9%, and bioenergy 10.7%. Solar carried the least risk.

TechnologyAverage construction cost overrun
Nuclear102.5%
Hydropower36.7%
Geothermal20.7%
Carbon capture and storage14.9%
Bioenergy10.7%

The study's coverage is what makes the nuclear figure usable. It modelled plants above 1 MW and transmission lines above 10 kilometres across coal, gas, nuclear, hydro, wind, solar, hydrogen and carbon capture, so the nuclear number sits inside a comparison of the whole infrastructure menu rather than a sample of the hardest reactors ever attempted.

The published summaries of the study disagree on one figure, and the disagreement is instructive. Chinese-language write-ups report that the average project ran about 40% beyond plan with a delay of about two years; one places that gap in construction cost, another places it in construction time. The difference is small in substance and revealing in practice, because the same result turns into different numbers depending on which measure a summariser reaches for. That is the everyday condition of nuclear cost claims, and it is why a shared definition does more work than another study.

Other institutions reach the same conclusion with less arithmetic. The IEA's global review found that high cost and long delays have to be addressed before nuclear can grow steadily. The Department of Energy's advanced reactor liftoff report puts the scale of the ambition at roughly 550 to 770 GW of advanced nuclear for a net-zero United States in 2050, and documents that overnight costs fall as designs move from first-of-a-kind to nth-of-a-kind.

Figures that circulate without a method deserve suspicion. A widely shared Reddit post cites an analysis of 160,000 global megaprojects giving average cost overruns of 120% for nuclear and 238% for energy storage. The sample and the definition differ from the Boston University dataset, and the two sets cannot both describe the same quantity at the same scale. Until the underlying dataset and its method are published, that 120% belongs in a footnote.

Transparency can raise the cost of the first units

The best argument against a registry is that publication is not neutral. Overnight costs fall as a design is repeated, so a first unit will always look worse than the fifth. Publish the first unit's overrun and the next buyer's lenders price it in; the cost of capital rises for units nobody has ordered yet, and the learning that would have brought costs down never happens. Campaigners would use it too. The Cable reports that demonstrators at COP31 called nuclear "too risky, too slow, and too expensive to address the climate crisis", and a permanent public ledger of delays is an efficient way to supply that argument with evidence.

Comparability cuts the same way. Reactors built in France, Turkey and the United States face different regulators, labour markets and supply chains, and a table that ranks countries by average overrun would record context as competence. A registry confined to nuclear would also misrepresent the problem, since the Boston University data put hydropower overruns at 36.7% and geothermal at 20.7%.

The objection is strong enough to change the design and not strong enough to abandon the instrument. Lenders and insurers already charge for undisclosed construction risk, and they charge it to every project in the queue because they cannot separate a competent owner from a serial overrunner. A verified record moves that premium onto the projects that earn it, which lowers borrowing costs for the builders who finish near schedule. Classification and a publication lag answer the learning-curve objection: a first-of-a-kind unit published with its status and a delay still tells the second buyer what to expect, without becoming the number that defines the programme.

What the registry has to record

The baseline should be the budget and schedule fixed at final investment decision, since earlier estimates are not commitments and later ones are revisions. Each entry needs capacity, reactor type, owner, host country and regulatory regime, a flag for first-of-a-kind status, and periodic deviation reports against that baseline. Cost and schedule belong in the same row, because a plant that finishes late and on budget fails differently from one that finishes on time and over budget, and only the pair shows which happened.

Coverage should extend across generation technologies, with grid and storage reported alongside for context. The registry needs a written definition of overrun: whether cost is nominal or real, which currency and exchange rate apply, and whether schedule is measured against a contractual date or a commercial operation target. Without that, the database invites disputes about the numbers instead of scrutiny of them.

Verification has to sit with a body that does not depend on the projects it audits, and it needs audit rights and a published method. The OECD has already studied the governance frameworks that drive learning and continuous industrial performance in nuclear construction, which makes the IEA, the Nuclear Energy Agency or the OECD the natural host. Publication should be lagged for first-of-a-kind units and immediate for repeats. Tying the data to procurement and finance, so that insurers, export credit agencies and utilities use it in their own decisions, would give owners a reason to report accurately rather than a reason to stall.

Small modular reactors need their own category. Almost every SMR project is a first of its kind, the economics rest on factory production that has not yet happened at scale, and the public record is thin because so few units exist. Starting the registry now, while the evidence is sparse, is the only way to find out whether the cost reductions in investor presentations survive construction. A registry launched after the first fleet is ordered would only confirm what had already been paid for.

The choice of host is the decision that determines whether any of this works. A body that depends on member governments for its budget will publish late and gently. A technical agency with an audit mandate will publish on time and embarrass someone, and that is what a delivery test looks like.

References

  • GreencarbonWorld: Senate Moves Toward Procedural Vote as COP31 Opens and Nuclear Debates Shift
  • Boston University Institute for Global Sustainability: Investment Risk for Energy Infrastructure Construction Is Highest for Nuclear Power Plants, Lowest for Solar
  • SolarZoom: Boston University study on construction cost overruns by technology
  • Sohu: Energy infrastructure construction risk, highest for nuclear and lowest for solar
  • Tonghuashun Finance: IEA chief Birol says global nuclear capacity under construction hits 40-year high
  • Zhenzhu Global: COP31 focuses on the global grid investment gap
  • JD Supra: Department of Energy report on advanced reactors sets forth pathway to commercial liftoff
  • RTO Insider: IEA Sees Momentum Toward New Nuclear Era, Obstacles
  • OECD: Unlocking Reductions in the Construction Costs of Nuclear
  • Toutiao: US prepares to restart nuclear power as experts warn of the cost
  • Reddit r/Futurology: A new analysis of 160,000 global megaprojects
  • The Cable: COP31 campaigners reject nuclear energy as climate solution

Related reading

  • Uprate, New Build or SMR? A Comparative Fuel-and-Waste Readiness Screen for COP31 Nuclear Projects | WorldIndustrialWeekly General
Brand logo

Industrial Weekly

In-Depth Weekly Insights on Manufacturing & Supply Chain

AutomationSupply ChainSmart ManufacturingLogisticsEnergyGeneralGreen CarbonWorld

© 2026 Industrial Weekly.

Cookie Notice

We use cookies to improve your experience and analyze website traffic. Read our Privacy Policy to learn more.